Project Management will be installing a slurry seal asphalt coat to some of the roads on campus beginning Monday, July 18. Below are the areas of maintenance along with the description of the work and dates it will be performed:
Area 1 (Main road dividing PCC and BYUH up to the McKay Gym parking lot)
- July 18, Prep
- July 19, Seal
- July 20, Stripe
Area 2
- Postponed until a later date
Area 3 (between Facilities Management Shops and Print Services parking)
- Jul 20, Prep/ Seal
- July 21, Stripe
During these dates, these areas will be completely closed off and all equipment on the asphalt in these areas, such as the trailers behind the CAC, must be temporarily relocated. The roads will be open on July 21, weather permitting.