WASH, BYUH's laundry machines contractor, will remove the old washers and dryers in the Hales and TVA and install new ones in August. The contractors will be using a forklift to move the machines to and from the locations. Two containers with the new machines for the Hales will arrive the week of July 25–29. The containers will be placed in or near the parking lots by Hales 3 and 5 and 4 and 6. One container for TVA will arrive the week of August 1–5. The container will be placed in the contractor’s fenced-in area near TVA A1. Please check the installation schedule for more details or contact Housing through email
Installation schedule:
- August 8–12: Hales
- Aug. 8: Hale 1 and 2
- Aug 9: Hales 3 and 5, 4 and 6
- Aug 10: Hales 7 and 8
- Aug 11: Hales 9 and 10
- August 15–19: TVA